This Office Refurbishment Project took place over a 4-month period, from the end of 2018, over the Christmas break, and into the New Year. It was vitally important to the client to upgrade their workspace to sit in line with the reputation and importance of the work they carry out daily, whilst keeping within their budget expectations.
The company now takes advantage of a huge open plan, well-lit space that is inviting for them and their prospective clients alike. The space has a new tea point and breakout area, meeting rooms, new shower, toilet and changing facilities and bespoke ‘celebration wall’ spanning nearly the full width of the office space.
Demolition and strip out of redundant fittings and existing fabric, electrical and mechanical elements as and where highlighted on architects’ drawings.
Removal of existing, unstable insulation to soffit.
Supply and installation of new rigid insulation to soffit.
Supply and installation of new partition walls and alcoves comprising veneered oak fascia’s and new timber doors.
Installation of new DDA and standard male and female WC and shower units.
Adjust existing raised access flooring.
Installation of a floating fine screed and once cured, supply and install new raised access flooring.
Supply and install new vinyl, tile and carpet floor coverings.
Carry out a restoration of existing Travertine flooring in office space.
Supply and install new Hunter Douglas, concealed grid ceiling.
Installation of new tea point, breakout & kitchen area.
Installation of new locker units to back of house area.
Complete redecoration of newly installed and existing structural walls.
Installation of decorative linings to feature walls.
Spray paint existing entrance curtain wall profiling.
Fabrication, supply and installation of bespoke celebration wall incorporating moveable folding partition walls.